Answer in brief
An offer that says “connection conditions issued” and one that says “connection agreement signed” describe two different projects. Start with the glossary: nineteen Polish terms you have to read correctly. Then run the ten checks in the order of a due diligence, from the document to a new application. PSE's own numbers on where storage sits in the connection queue follow the checks.
Your next step
You buy, invest or develop
Tell us which countries, sizes and stages you can act on, and we send you nothing that does not fit.
What happens to your enquiry →Polish terms you will meet in an offer
| Polish term | English | What it tells a buyer |
|---|---|---|
| warunki przyłączenia | grid connection conditions | The grid operator has set out how and where the project can connect. It is not yet a contract. |
| umowa o przyłączenie | grid connection agreement | A contract that reserves capacity, with milestones and payments to check. |
| GPZ (główny punkt zasilania) | main supply substation | The substation the project connects to. Its location and spare capacity decide the project. |
| decyzja o warunkach zabudowy (WZ) | zoning decision | Confirms that the plot may be used for the planned purpose where no local plan applies. |
| miejscowy plan zagospodarowania przestrzennego (MPZP) | local spatial development plan | If it covers the plot, it fixes the allowed use and replaces a zoning decision. |
| pozwolenie na budowę | building permit | Needed to start construction. Check validity and conditions. |
| cena do uzgodnienia | price to be agreed | The seller names no price. Ask for a price range before you read further. |
| dzierżawa | lease | The land is leased, not owned. Check term, rent basis and exit rights. |
| księga wieczysta | land and mortgage register | The register kept for each plot: it shows the owner, burdens and mortgages. Order an extract for every plot of the project. |
| użytkowanie wieczyste | perpetual usufruct | The land belongs to the State or a municipality and the project holds a right to use it. Check for how long and whether the right can be transferred. |
| służebność przesyłu | transmission easement | The right to run cables and lines across someone else's land. It should be entered in the land register for every plot on the route. |
| spółka projektowa (SPV) | project company (SPV) | The company that is party to the project's documents. A buyer usually acquires its shares, so who holds them and whether all are for sale matters. |
| operator systemu przesyłowego (OSP) i dystrybucyjnego (OSD) | transmission and distribution system operator | The transmission operator is PSE; a distribution operator is a regional company. Which of them issued the conditions decides whose rules apply. |
| zabezpieczenie | security (deposit or guarantee) | A guarantee or payment required with the connection agreement. Ask for proof it was filed. |
| wypis i wyrys z MPZP | extract and map from the local plan | The document shows what the local plan allows on one plot. Compare it with the use of a storage plant. |
| decyzja o środowiskowych uwarunkowaniach | environmental decision | The environmental consent decision. Ask whether the project needs one and whether it exists. |
| ostateczna decyzja | final decision | A decision that can no longer be appealed within the administrative procedure. For a building permit, ask for one that is final. |
| KRS | National Court Register | The company register. It shows who represents the project company and whether the person you are talking to can bind it. |
| umowa przedwstępna | preliminary agreement | An agreement to conclude the final contract later. Check the conditions and deadlines it sets. |
Ten checks, in the order a due diligence goes
- Which stage the project is at. The conditions or the signed agreement itself, with its delivery date. PSE counts conditions and an agreement in force as separate stages; its numbers follow below (PSE, aggregated connection information, read ).
- Where it connects. The grid company, the substation name and the voltage, from the document. Whether the node is full is a separate question (PSE, list of switchgear with no free connection places, read ): we answer it on GridBourse.
- The application: fee and attachments. The proof that the application fee was paid, and what was filed with it. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- Validity of the conditions. The delivery date and the validity written in the document; work out the expiry day yourself. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- The advance on the connection charge. The payment records of the advance and of any top-up. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- The agreement and its security. The signed agreement, the proof of the security and the milestones. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- The building-permit milestone. The final building permit, where the building law requires one, and the statutory deadlines. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- The grid-impact expertise. Whether an impact expertise exists and its conclusions are on file. PSE sets these rules out in its communiqué (PSE, communiqué on the change of connection rules, published , read ). The amounts and deadlines are on GridBourse.
- A shared connection point (cable pooling). Whether the project shares its connection point, and the sharing agreement if so. Our own question; read PSE's communiqué for the sharing rules (PSE, communiqué on the change of connection rules, published , read ).
- A new application: the ESOP portal. The portal confirmation if the seller files again. PSE runs the ESOP electronic connection portal; read its page for how new applications are filed (PSE, news item on the ESOP portal, read ).
The questions are our own list; each statement after them is what PSE writes on the linked page, on the day we read it. PSE's communiqué describes the process at PSE itself, so for a connection to a distribution company, ask that company.
How much storage sits at each connection stage
The ten checks open with the stage, so here are PSE's own numbers for it. We read the columns PSE labels MEE as electricity storage. PSE prints discharge and charge capacity separately and rounds every figure to one decimal place.
| Stage (PSE status) | What PSE counts here | Storage discharge, GW | Storage charge, GW | Solar PV, GW |
|---|---|---|---|---|
| Application in formal check | Not yet checked for completeness. | 0.9 | 0.9 | 0.3 |
| Application complete | Passed the formal check; technical and economic analysis under way. | 5.3 | 6 | 1.3 |
| Application incomplete | Left unreviewed or returned for missing documents. | 0.6 | 0.6 | 0.3 |
| Application withdrawn | Withdrawn by the applicant. | 4 | 4.4 | 1.1 |
| Conditions issued | Connection conditions have been issued. | 33.2 | 34 | 10.9 |
| Conditions refused | Connection conditions were refused. | 2.8 | 3 | 0.9 |
| Conditions expired | The statutory validity period of the conditions ran out. | 0.7 | 0.8 | 0.6 |
| Agreement in force | A connection agreement has been concluded and is in force. | 22 | 21.3 | 20.8 |
| Agreement ended | Terminated, withdrawn from or expired. | 0.4 | 0.3 | 0.4 |
| Plant connected | Electricity has been delivered under the agreement. | 0 | 0 | 0.3 |
| All stages | The sum of the rows above. | 69.9 | 71.3 | 36.9 |
Which voltage storage connects at
Own land near a 110 kV substation? Ask any developer who approaches you which voltage its connection point uses. Storage with conditions issued or an agreement in force adds up to 55.2 GW. Of that, 24 GW is at 400 kV, 8.8 GW at 220 kV, 16 GW at 110 kV and 6.4 GW on medium voltage (SN).
| Connection voltage | Storage discharge, GW | Storage charge, GW | Solar PV, GW |
|---|---|---|---|
400 kV | 24 | 24.2 | 7.6 |
220 kV | 8.8 | 8.9 | 4 |
110 kV | 16 | 15.9 | 11.1 |
| SN (medium voltage) | 6.4 | 6.3 | 9 |
| Total | 55.2 | 55.3 | 31.7 |
Is the substation already full?
The stage and voltage tables say nothing about one substation. For that, PSE publishes a separate list of switchgear with no free places. We keep its station-by-station table, with a checklist, on GridBourse.
How we read PSE's data
Our collector reads the PSE documents behind these figures every day and shows each figure with its source and the date we read it. The PSE connection page is where PSE publishes them. We checked PSE's robots.txt on : it allows these pages. We found no terms of use or licence statement on PSE's pages, so we store the figures only, with source and date, and link to the documents.
The seller, not only the project
An offer is worth what its seller can prove. Ask who owns the project company, whether every share is for sale, and whether the person you are talking to may sign. If you are the seller, put your file in the order above and mark what you do not hold yet.
Offers on boards such as Giełda OZE you read yourself: we copy no listing text and store no contact data from them. We name no price and give no valuation.
Looking for a Polish project?
We read your brief ourselves and introduce no one without your agreement.
Written by A. Manchev EOOD, Sofia. What happens to your brief is in the privacy notice.
Questions and answers
What should a buyer ask for beyond the conditions?
The agreement and the proof of its security. PSE states that a holder of earlier conditions files the security within 14 days of signing, or the agreement expires by law.
Does this cover distribution grids?
The source is PSE's communiqué on its own process. Ask the distribution company about the same steps in writing.
Does a connection condition mean a battery project will be built?
No. Conditions come before the agreement, and PSE's table lists them as separate rows. Conditions can also expire.
Do you check every offer on the boards?
No. We read what you send us. We do not scan or copy third-party boards.
Does it cost anything to send a brief?
No. A brief costs nothing and creates no obligation.
Sources and as-of dates
- PSE, aggregated connection information: pse.pl, retrieved .
- PSE communiqué: pse.pl, retrieved .
- PSE, communiqué on the change of connection rules pse.pl, retrieved .
- PSE, news item on the ESOP portal pse.pl, retrieved .
- PSE, list of switchgear with no free connection places pse.pl, retrieved .
- PSE, communiqué on impact expertises pse.pl, retrieved .